Skip To Content
  • Serving Plano and Collin, Dallas, and Denton Counties
(214) 668-8346
Two Legacy Tree Care arborists measuring the trunk of a mature oak with a diameter tape and checking it against a site plan, outside a commercial office building

Read From The Ordinance Itself

When Tree Work Belongs In A Construction Schedule

Nearly all of it happens before the equipment arrives.

Tree work reads like a site activity, so it gets scheduled like one, somewhere near clearing. Most of what these ordinances actually require happens months earlier, at concept and at permit, and the items that slip are the ones nobody sequenced.

(214) 668-8346

Crews dispatch in business hours.

Request A Property Walkthrough

Quick Walkthrough Request

Rather talk it through? (214) 668-8346.

  • Insured & Bonded
  • Serving the Plano Area Since 2005
  • Emergency Dispatch
  • Commercial Property Specialists

Tree Work Isn’t A Clearing Activity

On most programs it appears once, near the start of the site works, between mobilization and earthworks. That placement is reasonable and it’s wrong, because it’s the only tree item on the chart.

The obligations in these ordinances are spread across the whole project, from before the layout is drawn to years after practical completion. What gets missed isn’t usually a task. It’s a dependency nobody wrote down.

The Survey Is A Design Input

It’s the item most often placed too late, and the consequences are the largest.

A survey establishes what’s protected, where it stands and what constraints attach to it. If a perimeter zone runs up to thirty feet onto the site along a residential boundary, or a floodplain cap limits what proportion may be altered, or a specimen tree can’t be touched without a director’s approval, those facts constrain the layout rather than the budget.

Delivered at concept they shape a plan. Delivered after one, they produce a redesign or an application that argues for something the ordinance won’t permit.

Where Each Item Actually Sits

Four points in a program, and only one of them is on site.

  • At Concept, Establish The Constraints.

    A Legacy Tree Care arborist measuring a tree trunk with a diameter tape while holding a tablet, among dense woodland on undeveloped land

    What’s protected, where, and which areas carry an outright prohibition. This is the point at which trees can still change the drawing cheaply, and the only point at which changing it’s cheap.

  • At Submission, The Plan Travels With It.

    A numbered metal survey tag on a tree trunk, with a Legacy Tree Care arborist behind holding an open site plan and looking up into the canopy at a construction site

    The preservation plan is a condition on the plat, the grading permit or the zoning case it accompanies. Returned for revision, it holds up whatever it’s attached to rather than holding up the trees.

  • Before Grading, Fence And Inspect.

    A Legacy Tree Care arborist standing at a run of orange protective fencing enclosing a large tree at its drip line, on an active construction site

    Frisco wants fencing installed and inspected before the pre-construction meeting or the grading permit. That makes it a predecessor to mobilization, and a grading permit held for a fence is an avoidable delay.

Pull The Permit Against The Phase

Allen is the reason this deserves its own line. Trees approved for removal must be completely off the site within 90 days of the permit date, extendable one time by 30, and if the work runs past that a new permit has to be applied for and issued before it can continue.

On a single-phase site that’s rarely a constraint. On a phased development, a permit pulled at the start of a two-year program has expired long before the phase that needed it, and the second application is a cost and a delay that a scheduling decision would have avoided entirely.

The Tail Nobody Owns

Two of these cities put obligations well past the end of the job. Carrollton’s survival period runs two years from project completion; Allen’s runs three under a mitigation agreement.

Those dates sit beyond practical completion and beyond most retention releases. The project team that created the obligation is gone before it matures, which is how a replacement commitment becomes a surprise for an owner who was never told it existed.

It costs nothing to hand over a note of what was planted, under what obligation, and when the period ends. It’s simply that nobody’s role includes doing it.

Assign The Items Or The Sequence Fails

The survey belongs to design. The plan belongs to the submission package. The fencing belongs to the earthworks contractor and needs an inspection booked. The survival period belongs to the owner and needs a date in a diary.

Spread across four parties with no single owner, it’s the sequence that fails rather than any one task, and every one of the failures is visible months in advance to anyone looking at the whole set together.

Frequently Asked Questions

At concept, before the layout is fixed. The survey establishes what's protected and where, and that information constrains geometry: a perimeter zone, a floodplain cap or a large specimen can move a building. Commissioned after a layout is set, the survey stops being information and becomes a problem to be worked around.

With whatever it's required to accompany, which is rarely on its own. Carrollton wants it alongside a fill or grade permit, a plat, or a construction permit or zoning case. Wylie's goes with any development plan, site plan, plat, clearing and grading plan, erosion control plan or public improvement plan.

Before grading, and in Frisco before an inspection. Frisco wants it installed by the owner and inspected before either the pre-construction meeting or the grading permit, which makes it a predecessor to mobilization rather than an early site task. Plano requires it in place before grading as well.

Against the phase that will do the work, not against the design. Allen requires trees to be completely removed within 90 days of the permit date, extendable once by 30, with a new permit needed if the work runs past. On a phased site, pulling early converts a permit into a deadline.

Survival periods do. Carrollton runs two years past project completion and Allen three under a mitigation agreement. Those sit beyond practical completion, beyond most retention releases, and beyond the point at which a project team has moved on, which is why they land on the owner.

The survey, because it looks like a site activity and is actually a design input. The second is the fencing inspection, because it's a predecessor nobody put on the bar chart, and a grading permit held for a fence is a genuinely avoidable delay.

Removals largely yes, but pruning on oaks is a different question in this region because of oak wilt transmission risk during the vulnerable months. Where preserved oaks will need pruning as part of the works, the timing constraint belongs in the program rather than being discovered by the crew on the day.

Somebody, which is the point. The survey sits with design, the plan with the submission package, the fencing with the earthworks contractor and the survival period with the owner. Split across four parties with no single owner, the sequence is what fails rather than any individual task.

Where To Start

Three Ways To Settle The Compliance Question

Ordinance work usually has a date attached, and what closes it out is a document rather than a conversation.

Something Is Wrong Now

Call. You'll reach a person at any hour. We respond immediately during business hours, and first thing the next morning if you call overnight.

(214) 668-8346

You Want To Know What You Have

An arborist walks the property and documents what is standing on it, which is the record a permit application or a mitigation calculation gets built on.

Request A Walkthrough

Nothing Is Wrong Yet

Get on file before the season. Properties we already hold move faster on a storm night, because the crew isn't spending the first hour learning the site.

Set Up A Vendor Agreement

Commercial property only, fully responsible for the outcome, and we call 15 to 30 minutes before we arrive. The insurance clears before a truck moves. (214) 668-8346.

Request A Walkthrough

Tell Us About The Property

We'll walk the site, put the condition of every tree in writing, and give you a scope you can take to a board or a budget meeting. No obligation, and no pressure to decide on the spot.

If a limb is down or a lane is blocked right now, calling is faster than a form.

Call (214) 668-8346

  • Insured & Bonded
  • Serving the Plano Area Since 2005
  • Emergency Dispatch
  • Commercial Property Specialists

Send Us The Details

Tell us the property type and what you're seeing. We'll come back with next steps.

Request A Property Walkthrough
A limb over the entrance, a tree that looks unwell, a permit deadline, storm cleanup, an annual contract you want quoted, or getting set up as a pre-approved vendor before storm season.
Request A Walkthrough Call Now